INNA V. ELSHAIR 6715 Biscay Hbr, San Antonio, TX 78249 Telephone: (707) 474-7895 dinnamica@gmail.com ===================================================================== Summary
of Skills • Expert in
Planning, Scheduling, Analyzing, Executing, Monitoring, and Controlling
projects using Primavera Project Planner; • Certified
professional P5, P6 & P8 graduate by Oracle certified training provider; • Experienced
in EVMS (Earned Value Management System), cost control, cash flows,
Resource/cost loading, and resource requirement planning; • Expert
Microsoft Office application user, including MS Word, MS PowerPoint, MS
Excel; • Advanced
knowledge of MS Project to generate resource loaded schedules. Professional
Experience •
OCI Solar Power, San Antonio, TX
Project Controls ManagerJuly, 2014 - Present
Primary
responsibilities include: supporting contract execution by evaluating the
SOW, subcontractor’s proposals, cost estimates and drafting related exhibits, as well as
providing feedback based on the cost saving opportunity analysis; planning,
developing & maintaining IMS schedules for Alamo Solar Projects of more
than 700 MWac; guide the subcontractor in the resources and equipment
optimization as a part of the innovation program; identifying and evaluating
potential delays, risks and proposing mitigation steps; setting up cost
monitoring & reporting system and procedures, developing and maintaining
budget tracking and cash flow reports, including EV, CPI & SPI; support
engineering and QA/QC teams by developing the RFI & NSR workflows tailors
to business needs, as well as design tracking and communication procedures;
developing document filing structure unique to Solar business unit and
directing the SharePoint implementation. •
Gannett Fleming, Mill Valley, CA
March, 2014 – June, 2014 Project Controls/Scheduling Specialist Primary
responsibilities include: supporting civil/transportation projects’, such as East Bay BRT, Operations Communication Center Relocation,
San Leandro Bart Transit Center, needs in developing, managing EPC Master
schedule and analyzing the progress according to contractual requirements;
risk mitigation, cash flow forecast, change management, subcontractor invoice
review, and document control; reporting EV (Earn Value), CPI (Cost
Performance Index), SPI (Schedule performance Index), potential delay impact
and remediation solutions. •
Chevron, San Ramon, CA
November, 2013 – Feb, 2014 Project Control Engineer/Scheduler/Planner Under
Contract with Strategic Staffing Solution, I have provided the support for IT
Department Downstream Business Unit in developing, communicating, deploying
and monitoring planning & control processes and tools (e.g. schedule
maintenance, status reporting, resource management, change control, etc.); in
planning, creating and maintaining resource leveled project schedule(s) and a project budget utilizing customer’s best
practices and value adding processes; worked closely with the Project Manager
to provide analytical insights on the schedule & cost to enable
pro-active decision making; provided input to
project status reporting, including EV, Risk Analysis P10-P50-P90; schedule
and facilitate meetings; provide invoice analysis and tracking.
•
AECOM, Oakland, CAJune, 2012 – November, 2013 Project Controls Engineer I have
provided project controls support on several multimillion dollar Engineering,
procurement, and Construction (EPC) projects for AECOM Energy department,
mainly on PG&E projects, such as Whisky Slough and Turner Cut. It
involved rebuilding the entire gas injection and withdrawal platform by
phases, including Commissioning and Startup. My support included building and
maintaining cost loaded schedule with the recurring reporting to the client
of Earned Value, Look-ahead, Critical path and near Critical path, Summary by
Phases, by Systems, and areas using Codes; scheduling and cost analysis and
forecasting using Primavera 6.7 and 8, as well as, procurement tracking,
analysis, and expediting; sub & vendor tracking and reporting, claim
support, Monthly Financial Forecast and Cost Tracking Portfolio. •
Genentech, San Francisco, CA March, 2012 - May,
2012 Senior Scheduler/ Planner Under
contract with Harvest Technical Serv., Inc., I worked for Genentech on two
projects more than 500 million dollar on campus seismic upgrade and
infrastructure K directive project, building an integrated schedule for
Project Initiation and Conceptual Design Phases. Resource loaded schedule was
baselined and progressed. The reporting included: 3 week Look-ahead 10 days
back, Critical Path, Multi Float Path, Parallel Path, Earned Value, SPI,
sorted by Discipline and by Stages Reports. •
Sealaska Constructors, Seattle, WA Dec. 2009 – Jan.,
2012 Senior Scheduler/ Planner Under
contract with Projatech Inc., I worked remotely for Sealaska Constructors on
several multi-million dollar U.S. government projects, such as, Cressman
Dining Facility, Barksdale Air Force Base Pylon Project, and Fort Sill MATOC
Project. Converted schedules to U.S Military required SDEF format. Created
new schedules, cost loaded and progressed. Generated reports such as,
Baseline Schedule, 3-week look-ahead, critical activities, Earned Value,
Resource S-curve, Baseline comparison on regular basis. •
Chevron, Richmond, CA April, 2007 – Oct., 2009 Senior Scheduler/ Planner Under
contract with Projatech Inc., I worked on Chevron projects where I utilized
the best practices in scheduling, applying CPDEP, and schedule quality
assurance. Worked on several multimillion dollar projects with total budget
approx. $500 million; projects such as, Hydrogen Plant Replacement, and
Hydrogen Purity Improvements, Power Plant Replacement (using Cogeneration),
Continuous Catalytic Regeneration (Reformer Replacement), Gasoline
Hydro-Treater, Hydrogen Compressor Upgrade and Tie-In. Developed fully
resource loaded schedules for Engineering, Procurement, Construction,
Shutdown, Startup (Turnaround), Commissioning, Distributed Control Systems.
Responsibilities include project quality assurance, logic analysis, updating,
reporting, and monitoring. In addition, developing and implementing
scheduling standards and facilitating a unified integrated schedule for EPC
by bringing together multiple contractors. •
HG Engineering, Toronto, CA March 2005 – Feb.,
2007 Project Scheduler & Controller Under contract with AliZar Consulting Inc., I
worked for HG Engineering. The work involved project planning, scheduling,
executing, monitoring and analyzing the progress of engineering projects.
Assisted manager in developing cost control procedures and reports. Developed
construction resource leveled, hours and cost loaded schedules for cash flow
forecast and reported using S-curves, Performance Based Earned Value
Management System, CPI, SPI, TCPI, VAC, ETC. ADDITIONAL
SKILLS Developing
and generating the following: •
Executive Summary Report •
Activity Completion Curves •
Look-ahead reports •
Resource and Cost Loading Reports •
Baseline comparison report •
Cash Flow Analysis Report •
Graphs and progress curves for recurring meetings
and progress reviews •
Performance Reports based on Earn Value (EV),
Schedule Performance Index (SPI), •
Cost Performance Index (CPI), To Complete
Performance Index (TCPI), Estimate •
to Complete (ETC), Variance at Completion (VAC),
to help monitor Cost and •
Schedule performance Cost
management and control Resource
planning and budgeting Developing
OBS, RBS, WBS, and Cost Accounts. Creating
activities, establishing relationship, perfecting CPM logic diagram,
performing resource
and cost loading, generating baselines, streamlining projects, resolving issues
and delays, etc. Helping
managers in managing project cost through efficient Resources Planning, Cost Estimating
and Cost Control using CPI, SPI, TCPI Earned Value techniques. EDUCATION Bachelors
in Science, Mathematics & Physics Rovno State University, 1994 Primavera
Advanced Training P4, P5, P6 V.7 - 2007, 2010 Personal Financial Assistant Primerica Financial Serv., 2000 CSOC and CPDEP Training - 2013 |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Languages: |
Languages |
Proficiency Level |
|
Arabic |
Beginner |
|
|
English |
Fluent |
|
|
Russian |
Fluent |
|
|
Ukrainian |
Fluent |
|
|
|